Florida Power and Light hired us to install over 27,000 LF of silt fence for its new solar energy center near Wauchula, Florida.
We encountered several significant weather-related delays that required us to accelerate our original installation schedule on this project.
In order to complete the FPL Flatford Solar project in time, Florida Silt Fencing ran multiple crews to make up for the delays.